SAMPLE ONLY - Professional Estimating NZ - Concrete takeoff (illustrative figures),,,,, Project,Lot 14 dwelling (example),,,, Drawings,A-101 Rev B; S-201 Rev A,,,, Currency,NZD excluding GST,,,, Ref,Description,Unit,Qty,Rate,Total 03.01,Strip footing 300x600 20 MPa,m3,14.40,412.00,5932.80 03.02,Slab on grade 100 mm 25 MPa,m3,18.60,398.00,7402.80 03.03,Edge formwork slab,m2,31.20,58.50,1825.20 03.04,Reinforcing D12 bar 500E,t,0.86,3150.00,2709.00 03.05,Mesh SE62 laps incl.,m2,186.00,9.40,1748.40 03.06,DPM 250 micron taped,m2,194.00,4.10,795.40 03.07,Saw-cut joints,lm,42.00,6.80,285.60 ,,,,Subtotal,20699.20 ,,,,GST 15%,3104.88 ,,,,Total incl. GST,23804.08 Exclusions,Rock excavation; dewatering; testing; pump hire,,,,